Budget
Budget the whole lot on one sheet, not one quote at a time
List every job, measure it, price it in the unit bidders use, add a contingency and split the total into phases you can pay for.
By TerraElm Editorial Team Updated 8 min read
- Example subtotal (illustration)
- $19,700
- Example contingency, 10%
- $1,970
- Example total (illustration)
- $21,670
- Tool
- Job budget calculator
The short answer
A whole-lot budget is a list of jobs, each with a quantity, a unit price from a written quote, and a contingency for what the ground and the records have not told you yet. Then you split it into phases in the order the work must happen. In the illustration below, which uses made-up round prices, seven jobs add up to $19,700, a 10% contingency adds $1,970, and the total is $21,670.
Why one budget beats separate quotes
Quotes arrive one at a time. A fence bid, a patio bid and a lawn bid each look reasonable on their own. The total is what you can afford or not, and the order of the jobs decides when you pay. One sheet shows both.
It also shows where jobs depend on each other. A drain that is not built can ruin a new patio, so the drain sits above the patio in the plan and in the budget. The reasons are in plan the order of lot projects.
Step 1 and 2: list the jobs and measure them
Write one line per job. Use the jobs you actually want, such as drainage fixes, a fence, a patio, a tree removal, irrigation, beds and lawn. For each, record what must be measured and the unit bidders are likely to use. Units differ by trade and by company, so ask each bidder to state theirs. The quote units guide explains per foot, per visit and per tree.
| Job | Usual way to count it | Measure |
|---|---|---|
| Fence | Per linear foot, gates as separate lines | Run length in feet; see the fence and deck takeoff |
| Patio or walk | Per square foot | Length times width of each area |
| Sod or seed | Per square foot | Lawn area, from the lot plan tool |
| Tree removal | Per tree | Count, plus access for equipment |
| Drainage regrade | Allowance or per job | Sketch of flow, see drainage and grading basics |
Order materials by the same measures. The material order tool turns an area into quantities and adds waste. Give every bidder the same dimensions, so their numbers compare.
Step 3: get the unit price in writing
Get at least two written quotes per job, with the unit and the quantity on each line. A bare total hides what changed between bidders. Then put them on your sheet side by side. The method is in compare bids side by side.
Ask what each price assumes: easy digging, open access, hauling away debris, a permit fee. Where a bidder cannot know, such as rock under a patio or roots at a fence line, ask for an allowance and what happens if the real cost is higher or lower.
Lines that hide outside the quotes
Some costs never appear on a contractor's quote. Add a line for each one that applies to your lot, even if you do not know the amount yet. Mark it "to confirm" and fill it in when the office or the lab answers.
- Permit and review fees. Ask the building office what your job needs. See permits for outdoor projects.
- A survey or line check. Needed when a fence or wall goes near a line you cannot confirm.
- HOA application. Ask whether yours charges a fee. See HOA rules and your lot.
- A soil test. Penn State Extension lists it as a step before a new lawn, and its results tell you what the soil needs.
- Haul-off and repairs. Who removes debris, and who fixes the turf or the irrigation a crew damages.
Step 4: add a contingency
A contingency is money held back for costs you cannot see yet. It is not padding. Buried lines, hidden rot, rock, roots and a records surprise can all change a job after the quote. You choose the percentage by how much is unknown: a straight fence on a clear line needs less than a regrade on a wet lot.
For a reference point from outside landscaping, HUD's calculator page for its FHA 203(k) rehabilitation loans lists a required contingency reserve of 10% to 20% for structures 30 years old or older. That is a lender rule for repairing houses, not a yard standard. The example below uses 10% because it is round.
Step 5: split the total into phases
Group jobs in the order the work must go, then give each phase its own contingency. Phase one is usually records, 811 marks, drainage and any tree work. Hardscape follows. Irrigation, planting and lawn come last. Season matters too. Penn State Extension, for example, says the optimum seeding times in Pennsylvania are mid to late spring and late summer to early fall, so a lawn line may belong in a particular season.
Worked example with made-up numbers
| Job | Quantity times unit price | Cost | Phase |
|---|---|---|---|
| Drainage regrade and downspout extensions | 1 allowance at $2,500 | $2,500 | A |
| Tree removal | 1 tree at $1,800 | $1,800 | A |
| Fence | 150 ft at $30 per ft | $4,500 | B |
| Patio | 300 sq ft at $15 per sq ft | $4,500 | B |
| Irrigation | 6 zones at $400 | $2,400 | C |
| Planting beds | 400 sq ft at $5 per sq ft | $2,000 | C |
| Sod | 2,000 sq ft at $1 per sq ft | $2,000 | C |
The subtotal is $2,500 + $1,800 + $4,500 + $4,500 + $2,400 + $2,000 + $2,000 = $19,700. A 10% contingency is $19,700 times 0.10 = $1,970. The total is $19,700 + $1,970 = $21,670.
| Phase | Jobs | Jobs total | With 10% contingency |
|---|---|---|---|
| A | Drainage and tree removal | $4,300 | $4,730 |
| B | Fence and patio | $9,000 | $9,900 |
| C | Irrigation, beds and sod | $6,400 | $7,040 |
| All | Seven jobs | $19,700 | $21,670 |
Check: $4,730 + $9,900 + $7,040 = $21,670. Now change one number. If the fence bid is $36 per foot instead of $30, the fence costs 150 times $36 = $5,400, which is $900 more. The subtotal becomes $20,600, the contingency $2,060 and the total $22,660. The job budget calculator does this arithmetic for your own lines.
Steps to your own budget
- List every job you want in the next few years, in the order the work must go.
- Measure each one and write the quantity and the unit.
- Collect written quotes with the same scope and enter the unit prices.
- Multiply, add and apply a contingency that matches how much is unknown.
- Split into phases and mark each phase's season and permits.
- Update the sheet when a quote or a change order arrives, and call 811 before each phase that digs.
Questions homeowners ask
How much contingency should I add?
There is no single figure for yards. It depends on how much is unknown. HUD's FHA 203(k) calculator lists 10% to 20% for some house rehabilitation loans, which is a reference point, not a landscaping rule.
Should I budget by job or by phase?
Both. Price each job by quantity and unit, then group the jobs into phases in the order the work must happen. See plan the order of lot projects.
Are the prices in your example real?
No. They are invented round numbers for the arithmetic. Use your own written quotes, which depend on your lot, the season and the bidder.
Where do I run these numbers?
The job budget calculator handles lines, contingency and phases. Measure areas first with the lot plan tool.
Sources
- HUD: Standard 203(k) contingency reserve requirements (FHA Connection)
- Penn State Extension: Lawn establishment
- Common Ground Alliance: Before You Dig (811)
Checked on November 20, 2026. The prices in the worked example are invented for illustration and are not sourced. Real prices, permit fees and seeding windows vary by city, county, state and season. Ask bidders for written quotes and your county extension office for planting windows.
Next on the lot
-
Lot guide
Plan the order of lot projects
Records and 811, grading, hardscape, trees, irrigation, planting, lawn last, with a reason for each step.
-
Lot guide
Drainage and grading basics
Read grade, size roof runoff (748 gallons per inch on 1,200 sq ft) and move water without harming a neighbor.
-
Lot guide
Lot size vs yard size
Lot area minus house, drive and walks equals yard: a worked 8,400 sq ft example.