Skip to content
TerraElm

Liens and changes

Three papers that protect you after the contract is signed

A change order records what changed, a warranty says who fixes what, and a lien waiver shows that the people behind the contractor were paid.

By TerraElm Editorial Team Updated 8 min read

Any change
Written and signed
A warranty
Attach it to the contract
A mechanic's lien
Claim for unpaid work
Legal questions
Ask your state office
Illustration: a site plan with a change-order sheet pinned beside a fence run, and a pink flag on a lien notice stapled to a gate

The short answer

Jobs change once the crew sees the lot. Record each change in a written change order that states the work, the price change and the date change, and that both sides sign. Ask for any warranty in writing, attached to the contract. And learn how a mechanic's lien works: in general terms, an unpaid subcontractor or supplier can make a claim against your property, which is why states such as California and Oregon publish advice on lien releases. This is general information, not legal advice.

Change orders: one change, one signed page

A crew digs and finds a buried boulder. You decide to add a gate. The old fence turns out to be on a neighbor's side of the line. Each of these changes the price or the schedule. California's Contractors State License Board says added, removed or substituted work, and changed completion dates, should be recorded on a change order, including any price changes. Its guide adds that a signed change order becomes part of the contract and that all changes must be in writing and signed by both parties.

Massachusetts says the same in plainer terms: any modification to the original contract must be in writing and agreed to by both parties. A spoken "we'll take care of it" is hard to prove later. Even a small change deserves a signed line.

  • What changed. The work added, removed or swapped, with materials named.
  • Price change. An amount, plus or minus, and the new contract total.
  • Date change. A new finish date if the schedule moves.
  • Payment. When the extra amount is due. Keep it to a finished stage.
  • Signatures and date. Both parties, before the extra work begins.

Here is how the arithmetic works, using made-up numbers and not typical prices. Start with an $8,400 contract. Change order 1 adds a walk gate for $650, so the total is $9,050. Change order 2 drops the stain for a $420 credit, so the total is $8,630. Keep a running total on one sheet, and check it against the schedule of payments in contracts, deposits and payment schedules.

Warranties: what is promised, by whom, for how long

Massachusetts' contract page says any express warranty must be attached to the contract, and that goods sold in the state also carry implied warranties. The state attorney general's home improvement guide lists "guarantees or warranties for labor or materials" among the contract terms, and advises writing down all the warranties and verbal promises. A warranty that is not on paper is hard to enforce. Which warranty rules apply to your job depends on your state, so ask your attorney general's consumer office.

Workmanship

Covers the installer's labor. Ask how long it lasts, what it covers and how to report a problem.

Materials

May come from the maker, not the contractor. Ask for the maker's paperwork and who files a claim.

Plants and sod

Living things have conditions, such as watering. Ask what you must do and what the contractor replaces.

Exclusions

Read what voids the warranty, such as moving a fence or changing the drainage.

Ask for the warranty in the same document as the scope of work, signed and dated. Then file it with your survey, permits and receipts. These are the records you will want if you sell the house.

Mechanic's liens and lien waivers in general terms

A mechanic's lien is a claim made against property by someone who was not paid for work or materials. The CSLB guide says it is recorded with the county. Oregon's Construction Contractors Board says anyone who improves property, supplies materials or provides services can claim a lien if unpaid, including subcontractors and suppliers who never contracted with you. It adds that an owner who paid the general contractor in full can still be affected, and that a valid lien can lead to a court-ordered sale of the property.

A lien waiver or release is a signed paper in which the person who did the work gives up lien rights, in the amount stated. Terms and forms vary by state. Oregon advises owners to get signed waivers from everyone who sent a notice of right to a lien before paying the contractor. California's CSLB suggests that you:

  • get a list of all subcontractors and material suppliers who will work on the project;
  • have subcontractors sign lien releases when their portion of the work is finished; and
  • consider a joint check payable to both the contractor and the subcontractor or supplier.

Notice rules differ too. California says contractors must give consumers a "Mechanics Lien Warning," and Oregon requires a contractor who contracts directly with a residential owner to give an "Information Notice to Owner About Construction Liens" when the contract is over $2,000. Oregon adds that a contractor who skips it loses the right to claim a lien. Oregon notes that banks may ask each payee on a joint check to appear in person with identification.

A short checklist for the middle and the end

  1. Sign every change before the extra work starts, and update the total.
  2. Attach the warranty to the contract and store a copy with your lot records.
  3. Ask who else is working on the job: subcontractors, suppliers, equipment rental.
  4. Get releases as each stage is paid, in the form your state expects.
  5. Hold the last payment until the work is finished, the cleanup is done and the releases are in hand.

For the earlier steps, read contractor licenses and insurance. For terms used here, see the glossary.

Questions homeowners ask

Does every change need a change order?

Anything that changes the work, price or finish date should be written and signed by both sides. California's CSLB and Massachusetts both say changes belong in writing.

What is a lien waiver in plain words?

It is a signed paper from a contractor, subcontractor or supplier giving up the right to claim a lien for the amount paid. The forms and rules differ by state, so check yours.

Can a lien affect me if I paid my contractor?

Oregon's Construction Contractors Board says an owner who paid the general contractor in full can still be affected if a subcontractor or supplier goes unpaid. Ask your state board or an attorney how your state handles it.

Who enforces a warranty?

It depends on who gave it and what your state allows. Get it in writing and attached to the contract, then ask your state attorney general's consumer office. See the FAQ for more.

Sources

Checked on November 20, 2026. Change-order, warranty and lien rules vary by state, and lien deadlines and notice forms are set by state law. California, Oregon and Massachusetts are examples, not a rule for your address. This page is general information, not legal advice.